Environmental Impact Report

The proposed RSA project was originally evaluated by the District under the California Environmental Quality Act (CEQA) through preparation and circulation of a Draft, Recirculated Draft, and Final EIR (collectively, 2011 EIR) and related documents. (Those documents are available via the hyperlinks below.) The District, as the lead agency and project sponsor, certified the 2011 EIR and approved the RSA project on May 4, 2011. The District’s actions subsequently were challenged in a lawsuit filed in the Superior Court of California, County of Monterey on June 3, 2011.

In April of 2012, the adequacy of the 2011 EIR was argued at the trial court level and taken under submission by Monterey County Superior Court. Following the Court’s deliberation on the case, the Court found that the environmental analysis for Monterey Peninsula Airport’s runway safety area project did not satisfy the requirements of CEQA. Although the Court upheld many of the challenged portions of the environmental analysis, certain portions required further study.

In October 2012, the District issued the Revised Draft EIR that addressed those areas identified by the Court. On December 19, 2012, the District certified the Project Environmental Impact Report (Project EIR) for the Runway Safety Improvements Project (RSA Project), and concurrently approved the RSA Project (Resolution No. 1590).  The certified Project EIR (SCH #2009071104) for the Runway Safety Improvements Project (RSA Project) consists of the Draft EIR (October 2010), Recirculated Draft EIR (March 2011), Final EIR (May 2011), Revised Draft EIR (October 2012), and the Revised Final EIR (December 2012).

Following the District’s December 19, 2012 action, legal counsel for the District filed a Motion to Discharge (Motion) the Peremptory Writ of Mandate.  On July 3, 2013, the Court filed an unfavorable Intended Decision on District’s Motion.

In compliance with CEQA, the State CEQA Guidelines and the Settlement Agreement (¶6), District staff, with the assistance of Coffman Associates and Kimley-Horn and Associates, Inc., evaluated the environmental ramifications of the proposed modifications to the approved RSA Project.  Based on the results of that evaluation, an Addendum (November 2013) to the previously certified Project EIR has been prepared in accordance with State CEQA Guidelines Section 15164.

The Addendum concludes that any potential environmental impacts associated with the proposed modifications to the approved RSA Project were identified within the scope of the previously certified Project EIR, and that the environmental ramifications associated with the proposed modifications are the same as, comparable to, or less than those identified in the previously certified Project EIR.  Relatedly, none of the triggering parameters calling for preparation of a subsequent or supplemental EIR pursuant to State CEQA Guidelines Section 15162 and 15163 have occurred.

State CEQA Guidelines Section 15164(c) provides that the Addendum does not need to be circulated for public review.  The Addendum, however, was made available to the public on November 6, 2013, with a copy being posted via a hyperlink below.
EIR Addendum Cover

Addendum to Monterey RSA Project Environmental Impact Report – November 2013

 

EIR cover

Monterey Revised Final Environmental Impact Report – December 2012

Chapter 1 – Introduction

Chapter 2 – Errata of Revised Draft EIR

Chapter 3 – Comments and Responses (Part 1)

Chapter 3 – Comments and Responses (Part 2)

Appendix A – State Clearinghouse Confirmation Letter

Appendix B – Notices of Availability Provided for the Revised Draft EIR and Public Information Meetings

Appendix C – Public Information Transcripts and Meeting Materials (Part 1)

Appendix C – Public Information Transcripts and Meeting Materials (Part 2)

Monterey Revised Draft Environmental Impact Report – October 2012

Appendix A – Glossary of Terms

Appendix B – Agency Coordination and Public Outreach

Appendix C – Excerpts from Relevant Federal and State Standards and Regulations

Appendix D – 2012 FAA-Approved Airport Layout Plan (ALP) part 1

Appendix D – 2012 FAA-Approved Airport Layout Plan (ALP) part 2

Appendix E – Focused Carbon Sequestration Analysis

Appendix F – Monterey Peninsula Airport (MRY) Compliance Study

Appendix G – Monterey Peninsula Airport Traffic Study Validation

Monterey FINAL Environmental Impact Report – May 2011

Monterey Recirculated Draft Environmental Impact Report – March 2011

Monterey Draft Environmental Impact Report – October 2010

Chapter One – Project Description

Chapter Two – Alternatives

Chapter Three – Environmental Setting and Impact Analysis

Chapter Four – Other CEQA Analysis

Executive Summary

Appendix A – Glossary of Terms

Appendix B – Project Scoping Materials and Agency Coordination

Appendix B (continued)

Appendix C – Aviation Forecasts and Design Standards

Appendix D – Cultural and Paleontological Resource Surveys

Appendix E – Noise Modeling and Air Quality Input Assumptions

Appendix F – Botanical and Biological Information

Appendix F (continued)

Appendix G – Preliminary Geotechnical Investigation

Appendix H – Relocated Access Road Analysis

Appendix I – Draft Mitigation Monitoring Plan